5 minute read – Major 16-day railway overhaul completed in Manchester as part of the Transpennine Route Upgrade

©Network Rail
  • Work to reconstruct/strengthen railway bridges and upgrade track in central Manchester was completed by Network Rail this morning (16 August)
  • Railway lines between Manchester Victoria and Rochdale and Manchester Victoria and Stalybridge have fully reopened following successful completion of the work with final finishing touches being made on Sunday 22 August, Sundays throughout September and the weekend of 2/3 October
  • This forms part of the Transpennine Route Upgrade (TRU) which will bring faster, more reliable services to passengers travelling between Manchester and York, via Huddersfield and Leeds
©Network Rail

Railway passengers in Greater Manchester move one step closer to faster, more frequent, more reliable trains after major railway upgrades were completed on time between Manchester Victoria, Rochdale and Stalybridge.

Work took place from Saturday 31 July until Sunday 15 August to completely reconstruct railway bridges on Dantzic Street and Queens Road and strengthen and waterproof Bromley Street and Oldham Road bridges.

Over 3000m of track was upgraded and track remodelled between Manchester Victoria and Stalybridge. 17 new signals were also installed.

©Network Rail

Further work takes place as planned on Sunday 22 August, Sundays throughout September and the weekend of 2 and 3 October, to make the final changes with less disruption to passengers. All TransPennine Express (TPE) services will again be diverted into Manchester Piccadilly, with TPE services between Manchester Piccadilly and Liverpool being operated by rail replacement buses on Sundays. Buses will also replace Northern services between Stalybridge and Manchester Victoria calling at Ashton-under-Lyne.

This work is essential to enable more trains and faster trains to run in future. The newly renovated bridges now allow increased weight loading of more trains and the new and remodelled track will allow trains to run at faster speeds.

This milestone is a crucial part of the multi-billion-pound Transpennine Route Upgrade. This major railway upgrade programme will improve connectivity in the North of England by providing faster, more reliable services for passengers travelling between Manchester, Huddersfield, Leeds and York.

©Network Rail

Neil Holm, Transpennine Route Upgrade Director for Network Rail, said: “We’ve made major progress across Greater Manchester on this key part of the Transpennine Route Upgrade. Our teams have worked around the clock over the past 16 days to improve journeys for passengers.

“As well as bringing more reliable services, this complex upgrade will eventually allow more trains and faster trains to run on the busy route between Manchester and York.

“We carefully planned the work to keep passengers moving during the upgrade. I want to say a big thank you to passengers for their patience while the improvements took place.”

Kathryn O’Brien, Customer Experience Director for TransPennine Express added: “These works completed as part of the Transpennine Route Upgrade are the first step to improving capacity and journey times across the Pennines. We’d like to thank everyone involved in the engineering works that have taken place across the last 16 days, helping to create a more reliant and resilient railway for our customers to travel on. We’d also like to thank our customers for their patience throughout the works.”

Chris Jackson, Regional Director at Northern, said: “The Transpennine Route Upgrade is a vital part of the future of rail in the North and it’s great to see this first phase completed – paving the way for further enhancement work on this crucial business and leisure corridor.

“As an industry we have worked closely to keep disruption to a minimum, and our customers on the move, and we are all grateful for the understanding shown by those who rely on our services to get them where they need to be.”

©Network Rail

5 minute read – Major bridge reconstruction work starts in Manchester – passengers reminded to check journeys

  • Work to reconstruct and strengthen railway bridges in central Manchester has started and will continue until Sunday 15 August
  • Passengers travelling through Manchester Victoria are being urged to check their journeys at nationalrail.co.uk
  • This work is part of the Transpennine Route Upgrade (TRU) which will bring faster, more reliable services to passengers travelling between Manchester and York, via Huddersfield and Leeds

Railway engineers have started major upgrade work to completely reconstruct railway bridges on Dantzic Street and Queens Road and strengthen and waterproof Bromley Street and Oldham Road bridges in Manchester.

During the 16-day upgrade programme (31 July – 15 August) there are changes to services between Yorkshire and Manchester. Network Rail, Northern and Transpennine Express have built a plan to keep passengers moving on trains across the Pennines as much as possible.

Some journeys may need to be completed partly by bus, primarily between Rochdale and Manchester Victoria. The latest, state-of-the-art buses will be available to passengers so they can travel in comfort throughout.

Passengers looking to travel over this period are being urged to check nationalrail.co.uk.

Timelapse footage showing steel beams being lifted into place, with the help of a 650-tonne crane at Dantzic Street, has been released by Network Rail. Over 3000m of track is also being upgraded to bring smoother, more reliable journeys.

This work forms part of the Transpennine Route Upgrade (TRU), a multi-billion pound, transformative, long-term railway infrastructure programme between York, Leeds and Manchester which will improve connectivity in the North.

Neil Holm, Transpennine Route Upgrade Director for Network Rail, said: “Our improvement work in Greater Manchester is a key part of the Transpennine Route Upgrade (TRU), which will enable more trains and faster trains to run between Manchester and York in future.

“This major upgrade includes demolishing ageing railway bridges to install new ones, upgrading track and installing new signals. Though we can’t keep these railway lines open through Manchester Victoria while we do this, we’ve created diversionary routes so passengers can still get in and out of Manchester by train as much as possible.

“Thank you to passengers travelling this summer for your understanding while we deliver these much-needed improvements.”

Tricia Williams, Northern’s Chief Operating Officer, said: “It is welcome news that the railway continues to be invested in and the infrastructure improved upon.

“To complete these initial works there will be some planned changes to our services and our message to customers is very simple – please plan ahead and check your journey before travelling.

“To minimise disruption we will be running state-of-the-art replacement buses, offering clear customer information, including via digital and social channels, and will have more colleagues at stations to provide assistance both before and during the engineering works.”

Kathryn O’Brien, Customer Experience Director for TransPennine Express commented: “We’re delighted to see continued investment in the North of England’s railway as part of the Transpennine Route Upgrade. And with these works this summer, we will see a better, more reliable railway for our customers.

“To complete these engineering works, some of our services will be diverted and customers may have to change trains in Manchester, so we would advise those travelling to check before they travel. To help with those affected, there will be more railway colleagues at stations to help people get to where they need to be.”

Railcam Sheffield is LIVE!

We are delighted to reveal our latest installation, Railcam Sheffield.

For the last 10 months Covid-19 has limited us to very few installs and upgrades, dodging between lockdowns and travel restrictions, we have struggled to keep up with the mountain of locations we have to install with brand new cameras, or upgrade existing equipment.

One shining light has been the small number of hosts who are able to self install pre-configured equipment, and our host at Sheffield is one of those.

Shipped just last week, our host has got the equipment set up in his office window in no time, and we now have a stunning overview of the north end of Sheffield station, which has the added bonus of the Sheffield SuperTram thrown in for good measure.

Due to the camera being inside, we unfortunately can’t offer audio, but the PTZ (Pan, Tilt & Zoom) functionality of the camera gives us the option of the stunning images displayed below,

Railcam Sheffield will be available to Railcam Supporters from 10am on Friday 29th January.

Fancy becoming a Railcam Supporter?

For £4 a month or as little as £23 for the entire year, you can take advantage of many addition features, including Live Signalling Diagrams, addition Premium Cameras, Schedule information and much more…..

Find out more at https://railcam.uk/whatyouget.php